Welcome to the Course Maintenance blog for Blackwood Golf Club. The aim of this blog is to inform, educate and update on the work the course staff does to maintain and enhance the playing conditions for the enjoyment of the members. Check here throughout the year to get updates, news and view interesting pictures on what has been happening around the golf course.

Monday 30 September 2013

A Busy Month of Renovations


Sanding the 11th green

Greens were fertilised with an application of a biologically enhanced organic fertiliser, the week prior to the start of renovations, to promote active growth to aid with the recovery process.

Despite the inclement weather that gave us 35mm of rain for the week, greens renovations took place as scheduled. All greens were scarified on the Monday to a depth of 25mm; they were then cored using 19mm tines to 125mm depth over the next two days using a closer pattern (50mm x 50mm) than previous years to impact a greater surface area. Due to the rainfall the majority of greens were not sanded until Thursday, with some greens then receiving a top-up of additional sand on Friday morning (a total of @100 tonne of sand was used throughout the renovation process). The sand on the greens was worked into the core holes using a rotary brush and received their first cut at 4.5mm one week after coring. They were then reduced back to their normal height of 3mm in stages over the next week.  I am extremely pleased with the speed of the recovery of the greens and also the fact that we were able to achieve this with what I believe to be minimal disruption and inconvenience to the membership.

Renovation of tees has also been completed with all tees cored using 19mm hollow tines to a depth of 75mm to remove a percentage of the thatch that has built up since the autumn renovation. Tees have also been overseeded and then sanded.

Fairways have been sprayed with a combination of products to eradicate Poa annua, ryegrass and broadleaf weeds that have germinated since the last application of product.


Friday 6 September 2013

August Weather Data



August 2013
August 2012
average
Rainfall
136.5 mm
107.5 mm
112.5 mm
Year to Date
618.5 mm
739 mm
610.6 mm
No. of rain days
19
17
-
Average Temp.
16.3°C
13.4°C
-
Average Humidity
77.8%
77.5%
-

The above average rainfall we received this month has meant that this winter has exceeded last year and been the wettest since 2004. On top of a very wet July this has meant that the course is now starting to become very wet and boggy in the usual places. The upside of this is that the main dam is now full and overflowing. 

The main emphasis of last month’s workload can be split into two parts –

  • The first two weeks seeing staff concentrate on the removal and clean up of the River red gums approved by the council for removal from the righthand side of the 5th fairway. The stumps were ground out prior to the heavy rains and we are now waiting for the ground to dry out to allow us to complete the clean-up.
  • The second two weeks saw staff working on the tasks needed to drain the two bunkers on the second hole. The works needed to carry out the project were undertaken in the following stages –
Ø  Old sand removed
Ø  Re-grade base of bunker
Ø  Dig out drainage lines (herringbone system)
Ø  Install geofabric liner to base of bunker
Ø  Install drains (100mm slotted ag-drain/stone/shade cloth)
Ø  Add sand shellgrit mix
Ø  Consolidate base and shape/pack faces

Following the Ladies Foursomes Championship, spring greens renovation will be carried out, with coring and sanding of greens on the front nine scheduled for Monday 16th September and the back nine on Tuesday 17th September. All greens are also being scarified as part of the renovation process, with this operation being carried out by a contractor throughout the day on the Monday.

Renovation of tees are also scheduled to be carried out this month, with tees being cored to a depth of 75mm and then oversown and sanded to complete the renovation process.

Fairways will be sprayed for Poa annua that has germinated since the last application of product. Areas of broadleaf around the course will be also continue to be targeted as time permits over the coming weeks

Friday 23 August 2013

A More Typical Winter Week

15th approach looking back from the green
This week has been a very stark reminder of previous winters with 78mm of rain falling since last Saturday making the course extremely wet underfoot, hence the decision to ban carts. The course is now at saturation point and any further rain we receive just compounds the issue. On a positive note, the main 15th dam has reached full capacity with the overflow starting to discharge excess water yesterday morning. 
2nd bunker prior to the start of drainage work
This week work has started on installing better drainage into both of the bunkers at the 2nd green. The bunkers have been stripped of the old sand, both the bases rough shaped and the outlet for the front bunker has been dug across the fairway to the masterline which runs down the lefthand side of the fairway. The terrible weather throuhout the week has slowed progress more than I would have liked, but with better weather forecast for next week we should be back on schedule to complete the project by the end of next week. 

Friday 2 August 2013

A Return to Blogging


 
18th Green - Saturday 20th July
 

May 2013
May 2012
average
Rainfall
85.5 mm
125 mm
101 mm
Year to Date
189 mm
317 mm
243 mm
No. of rain days
11
17
-
Average Temp.
19.9°C
15.7°C
-
Average Humidity
68%
74.8%
-
 

June 2013
June 2012
average
Rainfall
92.5 mm
208 mm
125 mm
Year to Date
281.5 mm
525 mm
368 mm
No. of rain days
11
18
-
Average Temp.
16.5°C
12.5°C
-
Average Humidity
78.5%
79.2%
-
 
The weather pattern for both May and June was very similar with long, warm dry spells broken up by periods of heavy rain. However, both months received below average rainfall, and up until the 122.5 mm of rain we received between the 18th and 23rd of July the levels of all of the dams were lower than normal for this time of year. That all changed when all of the dams virtually filled over the corresponding period. The level of the main dam is approximately 1 metre below the spillway and I am now fairly confident that it will be full before the end of August given that the long term forecast for the next three is for above average rainfall.  Groundwater levels are now at the point where any further rainfall that we receive will be captured through the drainage system and discharged into the dams.

The 200.5 mm of rain that we received over the past month has meant that this July has been our wettest since 1996. As can be seen from the chart below, the past three months have also been significantly warmer than average and this has enabled us to spend a larger proportion of staff time on course presentation than normal and this is noticeable in the general condition of the course. The fairways, in particular are as dense and green as they have ever been for July.


July 2013
July2012
average
Rainfall
200.5 mm
106.5 mm
130 mm
Year to Date
482 mm
631.5 mm
498 mm
No. of rain days
16
20
-
Average Temp.
14.8°C
12.5°C
-
Average Humidity
81.6%
78.8%
-

CFS Volunteers burning the reeds in the dams
 

Wednesday 15 May 2013

The Start of the Winter Rains?

Our resident kangaroo on the 15th hole

The much cooler temperatures and the 50mm of rain of the past few days is hopefully the start of our normal winter weather pattern. We are currently sitting at @100mm of rain less than our average for this time of year, this obviously means that we need above average winter rains to recharge the bore aquifers and refill our dams in preparation for next summer.

The rain we have recieved has thouroughly washed the recent fairway gypsum application into the profile. Greens have received an application of fungicide to target an outbreak of Dollar spot and Anthracnose that has flared up due to the high disease pressure caused by the warm temperatures and high humidity during the last month.

All greens, tees and surrounds will receive applications of liquid fertilizer and iron in the coming weeks. These scheduled monthly applications are to help to maintain acceptable nutrient levels, colour and aid with disease suppression throughout the winter months.

A second application of pre-emergent product will be applied to fairways to give us further Poa annua control over the next 12-14 weeks. Poa annua that is present will also be targeted with a post-emergent product.

Monday 6 May 2013

April Course News


April 2013
April 2012
average
Rainfall
42 mm
44.5 mm
54 mm
Year to Date
103.5 mm
192 mm
141.5 mm
No. of rain days
7
6
-
Average Temp.
23.5°C
22.1°C
-
Average Humidity
64.2%
61.6%
-

Once again April provided us with a very similar weather pattern to the previous two months; a very dry start to the month with above average temperatures giving us the warmest April in the last seven years, and then some much needed rain at the end of the month which significantly boosted the total for the month. The 25mm of rain that fell on the 21st of April was the biggest single day rainfall that we have received since the 17th of August last year, a period of approximately eight months.

In lieu of a full autumn renovation, this year greens were mini-tined and fertilised with an application of a biologically enhanced organic fertiliser; this will further improve the health, vigour and condition of the sward prior to the start of winter.

Further landscaping works to continue to improve the area at the 11th/15th tee paths have been undertaken, with a large number of positive comments being received from members.
A significant amount of staff time has again been spent on clearing the storm debris generated from the strong winds we received throughout the month.
 Gypsum applied to 1st fairway
An application of @8 tonne/Ha of Gypsum was applied to all fairways using our own machinery and labour. The dry weather at the time of application also meant that we were able to dragmat the gypsum into the fairways straight away meaning less impact on play than in previous years.
Tasmainian Blue Gum at clubhouse prior to maintainence pruning
After maintainence pruning